Dispatch: Poorhouse Road project delayed in Oktibbeha County

Tim Pratt

STARKVILLE — More than a half dozen contractors showed up at the Oktibbeha County Board of Supervisors meeting Wednesday to find out who would win the bid for the Poorhouse Road construction project, but the group left without any answers.

Supervisors returned unopened bids to eight contractors because an issue with right-of-way acquisition has delayed the project, County Administrator Don Posey said.

District 1 Supervisor Carl Clardy said the county needs to get appraisals done on “two or three” properties because the descriptions of the properties were inaccurate during the initial right-of-way acquisition process. After the lands are appraised and agreements are reached with the property owners, the county intends to put out bids for the project once again, Clardy said.